MANUFACTURING QUALITY CHART



COMPILED BY TEAM MEMBER 2
TEAM MEMBER 3 TEAM MEMBER 4
SUPPLIER Webroy (Pty) Ltd MQC No
CUSTOMER REV No.
PART NAME DATE INITIATED
PART No. REVISION DATE 2024/09/26
    LAST REVIEW DATE 
WEBROY STOCK CODE STATUS
MANUFACTURING LOCATION Webroy SAFETY CRITICAL
MQC TYPE
Current
Process Flow Key

Process TypeImage
PARTS STOCK
COMPONENT PART
PROCESS OPERATION
SAMPLING INSPECTION
100% INSPECTION
TRANSPORT
Responsible
Confirmation Level Key
NameImage
OPER
T/L
SUPERVISOR
MNGR
OPER
T/L
SUPERVISOR
MNGR


PROCESS FLOWNONAMEWORK ELEMENTCHECK ITEMRANKPROCESS CRITERIONINSPECTION METHODINSPECTION PLANFREQUENCYInspection No.(s)Work InstructionsRESPCHECK SHEETCONFIRM'N LEVELREACTION PLAN 
1Receiving raw material - Stores PersonnelReceivingRaw material Check for correct quantity delivered, type and diameter.Visual inspection and verification as per orderDelivery Note and orderEvery Batch 1090
Goods Receive Note Book / Delivery Note hould there be any discrepancies inform production planner / supplier immediately and make a note on P.O.D
2Move material to receiving storage areaTransportRaw material Store material correctlyVisual InspectionAs per FIFO SystemEvery Batch Visual inspection If difficulty occurs in storing raw material properly inform Stores Coordinator
3Inspection of raw material by QA personelInspectionRaw material SC Correct Diam 3.8mm (+- 0.035mm) Correct - Spring wire. EN 10270-1. WIRE/SBS3/0380. Correct tensile - 1373mpa to 1569mpa - No rusty wire / no score marksVisual Inspection / MicrometerAs per incoming raw material inspection QD207Every consignment 6080
1120
Goods receive notebook / Buff tag and record findings on electronic sytem Any non-conforming raw material shall be placed on hold and isolated. Raise SRAN and inform Stores Coordinator
4Move raw material to dedicated area for storageTransportRaw material Safe stacking of wire coils as per allocated areas and FIFO systemVisual InspectionAs per FIFO SystemOn receiving Identification tags Any difficulty experienced during this activity report to Stores Coordinator
5Issue wire to productionIssuingRaw material Correct wire to be issued as per route card.Verification as per buff tag. Setter to verify wire diameter with correct micrometer/vernier caliper.Every coil issued to production.Every job as per request Route Card Should the incorrect wire be issued to production stop process, correct and inform Stores Coordinator
6Form wire on Wire FormerFormingForming SC As per fitment in checking fixture Visual inspection.First Off In process inspection of 2 parts and last-offEvery kanban trolley 20475
20476
20477
1164
Record on BIS card Should any incorrect part be formed stop process. report to team leader.
7LTHTStress relieveStress relieve SC Correct temperature 300C (+- 20C) for 15 minutesVisual inspection of oven temperatureVisual inspection of temperature. Every batch Visual verification Any difficulty experienced during this activity stop the process and report to team leader
8Load wire forms on kanbanLoadingLoading Load wires correctly on kanban. Correct wires loaded onto kanban.Visual inspection after LTHT.Full KanbanEvery batch NA Any difficulty experienced during this activity stop the process and report to team leader
9Load wire forms into mouldLoadingWire forms Correct loading of wire forms Visual inspectionAs per work instructionEvery part N/A Any difficulty experienced during this activity stop the process and report to team leader
10Moulding of wire formsMouldingMoulded seat cushion SC Correct injection as per requirement. Correct Mould parameter settings. Correct purging and pre check. Plastic hopper temperature control = 79 - 83 Degrees.Visual Inspection. As per job requirementEvery part 20461
20474
1203
Record on online inspection system Any difficulty experienced during this activity stop the process and follow stop, call wait procedure.
11Strip part from mould and inspectStripping and inspectingMoulded product Correct injection No missing pieces of plastic No sprue, No sharp edges Overmoulded wires to be completely covered, look for under shooting. Ref. CAR 48363Visual Inspection1 Finished partEvery part 16456
16458
16460
1194
Record on online inspection system Any difficulty experienced during this activity stop the process and report to team leader
12Load parts into binPackingCompleted products Correct quantity 15 parts per bin / 25 bins per palletVisual inspectionAs per works orderEvery job as per request FA Card Any difficulty experienced during this activity stop the process and report to team leader
13Transport part to storesTransportCompleted products Correct bins and correct quantityVisual in spectionAs per works orderEvery order FA Card Any difficulty experienced during this activity stop the process and report to Supervisor
14Receipt parts into storesReceiptingCompleted parts Correct quantity to be entered into stock systemVisualEvery batch.Every order 1094
FA Card Any discrepancy shall be reported to stores coordinator
15Dispatching of partsTransportCompleted parts Correct loading of boxes and safe handling during transport activityVisualAs per job orderEvery order 1101
Delivery note / Invoice Any difficulty experienced during this activity report to Stores Coordinator
16Layout function inspectionInspectionInspection Full dimensionalAs per drawing and customer requirements1 Complete partAs per schedule Audit sheet Should the functional layout fail, the production manager shall be reported immediately.