MANUFACTURING QUALITY CHART



COMPILED BY TEAM MEMBER 2
TEAM MEMBER 3 TEAM MEMBER 4
SUPPLIER Webroy (Pty) Ltd MQC No
CUSTOMER REV No.
PART NAME DATE INITIATED
PART No. REVISION DATE 2023/11/21
    LAST REVIEW DATE 
WEBROY STOCK CODE STATUS
MANUFACTURING LOCATION Webroy SAFETY CRITICAL
MQC TYPE
Current
Process Flow Key

Process TypeImage
PARTS STOCK
COMPONENT PART
PROCESS OPERATION
SAMPLING INSPECTION
100% INSPECTION
TRANSPORT
Responsible
Confirmation Level Key
NameImage
OPER
T/L
SUPERVISOR
MNGR
OPER
T/L
SUPERVISOR
MNGR
L&J


PROCESS FLOWNONAMEWORK ELEMENTCHECK ITEMRANKPROCESS CRITERIONINSPECTION METHODINSPECTION PLANFREQUENCYInspection No.(s)Work InstructionsRESPCHECK SHEETCONFIRM'N LEVELREACTION PLAN 
1Receiving and verification of raw material by stores personnelReceivingRaw material Check for correct quantity delivered, type and diameterVisual inspection and verification as per orderDelivery note and orderEvery batch 1090
Goods receive note book / delivery note Should there be any discrepancies - inform Production planner / supplier immediately and make note on POD
2Move material to receiving storage areaTransportRaw material Store material correctlyVisual inspectionAs per FIFO SystemEvery batch visual inspection and FIFO Board If difficulty occurs in storing raw material properly, inform Stores Coordinator
3Inspection of raw material by QA PersonnelInspectionRaw material Correct material 7.0mm +/- 0.08mm mild wire. Specification - SAE1008. Tensile range - 500mpa to 750mpa. No pitted rust, no score marks, no excessive drawing soapVisual inspection MicrometerAs per incoming raw material inspection planEvery consignment 9191
1120
Record on on-line inspection Any non-conforming raw material shall be placed on hold and isolated. Raise a SRAN and inform stores coordinator
4Move raw material to dedicated area for storageStorageRaw material Safe stacking of wire coils onto rack as per allocated areas and FIFO SystemVisual inspectionAs per FIFO SystemOn receiving FIFO information board and rack identification Any difficulty experienced during this activity report to Stores Coordinator
5Issue wire to productionIssuingRaw material SC Correct wire to be issued as per job cardVerification as per buff tagEvery coil issued to productionEvery job as per request Route card Should the incorrect wire been issued to Production, stop process, correct and inform Stores Coordinator
6Form wire on 12mm HuronFormingProduct SC Part shall be formed with the legs flat or have a MAX gap of 0.9mm as this is critical for the stamping process. Leg length is 42mm +/- 0.5mm. Part shall not sit on the pins. Appearance -No burrs, rust, Marks, Damage to finish. Overall length shall be 221mm. Visual inspection on Checking fixture and on a flat surface to check flatness using a feeler gauge. Measure overall length with a tape measure. Parts shall drop fit in checking fixture. Both legs shall sit flat when either is held down.As per work instructionFirst-off at start of production. In-process 9 parts every hour and last-off 7272
7273
10368


1163


Record on on-line inspections Should the first-off sample fail stop process and reset machine and re-do first-off
7Move parts for stampingTransportProduct Correct handling of parts during this activityVisual inspectionN/AEvery batch N/A Any difficulty experienced during this activity stop the process and report to team leader
8Stamping parts on 80 Ton pressStamping/flattening Product Legs shall be flat or have a max gap of 0.4mm, use a 0.5mm feeler gauge to confirm gap - gauge should not fit through. Stamping thickness - 4.7mm - 5.0mm. Gibb height - 323mm. LH back is 65.7mm, LH front is 66.2mm, RH back is 66.2mm, RH front is 66.6mm. Overall length is 222mm.Visual inspection. Check part using thickness with a vernier and gap check with a feeler gauge. Both legs shall sit flat when either is being held down.As per work instructionFirst-off at start of production. In-process 9 parts every hour and last-off 7274
10369
10370

1199

Record on on-line inspections Any non-conformance shall be isolated - raise NCR and put a hold card and be placed in quarantine store - inform Quality Manager
9Pack partsPackingProduct Correct quantity 250 per boxVisualas per customer requirementEvery job F/A Card Should the quantity be incorrect stop process, verify quantity and add/remove parts to meet quantity required
10Transport products to storesTransportProducts Correct quantitiesVisual inspection As per works orderEvery batch F/A Card Should difficulty occur during transport inform Supervisor
11Receipting product to storesReceiptingProducts Correct quantity to be entered on to the stock systemVisualEvery batchEvery order 1094
F/A Card Any discrepancies shall be reported to the Stores Coordinator
12Dispatching of productsTransportProducts Correct loading of bins and safe handling during transport activityVisualEntire orderEvery order 1101
Delivery note / invoice Any difficulty experienced during this activity report to Stores Coordinator
13 Internal product audit inspectionInspectionProduct SC Full dimensionalAs per customer requirements1 Complete productAs per schedule Audit sheet Should the part fail to meet the requirements, the Production manager shall be informed immediately.