MANUFACTURING QUALITY CHART



COMPILED BY TEAM MEMBER 2
TEAM MEMBER 3 TEAM MEMBER 4
SUPPLIER Webroy (Pty) Ltd MQC No
CUSTOMER REV No.
PART NAME DATE INITIATED
PART No. REVISION DATE 2022/06/09
    LAST REVIEW DATE 
WEBROY STOCK CODE STATUS
MANUFACTURING LOCATION Webroy SAFETY CRITICAL
MQC TYPE
Current
Process Flow Key

Process TypeImage
PARTS STOCK
COMPONENT PART
PROCESS OPERATION
SAMPLING INSPECTION
100% INSPECTION
TRANSPORT
Responsible
Confirmation Level Key
NameImage
OPER
T/L
SUPERVISOR
MNGR
OPER
T/L
SUPERVISOR
MNGR


PROCESS FLOWNONAMEWORK ELEMENTCHECK ITEMRANKPROCESS CRITERIONINSPECTION METHODINSPECTION PLANFREQUENCYInspection No.(s)Work InstructionsRESPCHECK SHEETCONFIRM'N LEVELREACTION PLAN 
1Receiving and verification of raw materialReceivingRaw material Check for correct quantity delivered, type and diameter (4.5mm)Visual inspection and verification as per orderDelivery note and orderEvery batch Goods receive notebook / delivery note Should there be any discrepancies inform production planner / supplier immediately and make a note on P.O.D
2Move material to receiving storage areaTransportRaw material Store material correctlyVisual inspectionAs per FIFO systemEvery batch Visual inspection and FIFO board If difficulty occurs in storing raw material properly inform Stores Coordinator
3Inspection of raw material by QA personnelInspectionRaw material Mild black wire. SAE 1010/1008. WIRE/MBH2/0450. Correct diameter 4.5mm +/- 0.08. No score marks, no rust on wire and correct tensile- 550mpa to 750mpaVisual inspection and MicrometerAs per incoming raw material inspection QD207Every consignment 6163
1120
Goods receive notebook / Buff tag and record findings on electronic system. Any non-conforming raw material shall be placed on hold and isolated. Raise SRAN and inform Stores Coordinator
4Move raw material to dedicated area for storageTransportRaw material Safe stacking of wire coils as per allocated areas and FIFO systemVisual inspectionAs per FIFO systemOn receiving FIFO information board and identification tags Any difficulty experienced during this activity report to Stores Coordinator
5Issue wire to productionIssue wire to productionRaw material SC Correct wire to be issued as per job cardVerification as per buff tag and Setter to measure wire diameter with vernierEvery coil issued to productionEvery job as per request Route card Should the incorrect wire be issued to production stop process, correct and inform Stores Coordinator
6Form wire on ZukronFormingWire form SC Form wire as per checking fixture. Fitment - Part must drop fit nn C/F. Parts Must Sit Flush In C/F Grooves. Harmfull Burrs Not Allowed. No Score Marks On Parts. No Rust On Parts. Legs parallel. Width dimension = 20.5mm +/- 1.Visual Inspection and verification on final checking fixture. First-off verification by Q.AAs per work instructionFirst-off at start of production. In-process 9 parts every hour and last off 4078
4079
10344
1092
Record on electronic system Should the first-off sample fail stop process and reset machine and re-do first-off
7Packing of final productPackingProduct Correct quanity = 100 per bin. Bin No. 4316VisualAs per supplier packaging specificationEvery job F/A Card Should the quantity be incorrect, stop process, verify quantity and add/remove products to meet quantity required
8Transport product to storesTransportProduct Correct quantitiesVisual inspectionAs per works orderEvery batch F/A Card Should difficulty occur during transport inform Supervisor
9Receipting product to storesReceiptingProduct Correct quantity to be entered on to the stock systemVisualEvery batchEvery order 1094
F/A Card Any discrepancies shall be reported to the Stores Coordinator
10Dispatching of productsTransportProduct Correct loading of bins and safe handling during transport activityVisualEntire orderEvery order 1101
Delivery note / invoice Any difficulty experienced during this activity report to Stores Coordinator
11Layout functional inspectionInspectionProduct SC Full dimensionalAs per customer requirements1 Complete productAs per schedule Audit sheet Should the functional layout fail the Production manager shall be informed immediately.