SAFETY
Gloves and ear plugs are to be worn throughout this operation.
Be careful of pinch points. Keep fingers clear at all times when the machine is operating.
SETUP & PREPARATION
Ensure the correct wire has been issued by validating GRN buff tag against the route card.
On the production system log the time as "Setting."
Load the Part Recipe found in the location "part recipe location" and prepare a First-Off sample.
Once the first-off is correct, on the production system end the "Setting"downtime and enter the job number and operation to start the job.
Enter the first-off inspection results in the production system.
QUALITY CHECKS
Formed part
The following checks should be performed:
Examples of Good and NG parts:
QUALITY INSPECTION
REJECTS
Scrap / Reject bins are to be emptied at the end of end job or at the end of shift if the job is running at the end of shift
PERFORMANCE TARGETS
Once the job has been logged on the system, you will be able to see the production figures and targets including
The picture to the left provides and example.
Production figures are to be logged on the system every hour.